Jack’s Floating Banana Party Company is planning to add a new party vessel for the upcoming season. Jack has identified several activities that must be finished before the start of the season. Use the following information:

a)

Identify the critical path.

Critical path is=

b)

Calculate the expected project length.

Expected project length = ______________________weeks.

Activity Activity Time
(weeks)
Immediate
Predecessor(s)
A 5 none
B 5 none
C 6 A
D 3 B
E 5 C, D
F 10

D