Jack’s Floating Banana Party Company is planning to add a new party vessel for the upcoming season. Jack has identified several activities that must be finished before the start of the season. Use the following information:
a)
Identify the critical path.
Critical path is=
b)
Calculate the expected project length.
Expected project length = ______________________weeks.
Activity | Activity Time (weeks) |
Immediate Predecessor(s) |
A | 5 | none |
B | 5 | none |
C | 6 | A |
D | 3 | B |
E | 5 | C, D |
F | 10 |
D |